CLIENT |
PROJECT
DESCRIPTION |
18-May-07 |
Shell Eastern Petroleum |
Design and build
a new 100m-high reinforced concrete multi-flue
stack as part of the ECC expansion project
at Shell's Pulau Ular refinery in Singapore. |
8-Mar-07 |
Shell
Eastern Petroleum |
Design
and build a new 100m high reinforced concrete
single-flue stack as part of the SBRM project
at Shell's Pulau Bukom refinery in Singapore. |
27-June-06 |
The Ratchaburi Electricity
Generating Co., Ltd (RGCO) |
Major shutdown
repair to Ratchaburi Power Station chimney
in Thailand. |
16-Mar-06 |
Senoko
Power Ltd |
Inspection, Maintenance and Washing of Stage
II and III Stacks and Its Concrete Windshields
at Senoko Power Station. |
4-Nov-05 |
Shell Eastern Petroleum |
CD3 fan scaffold. |
2-Nov-05 |
McLarens (Thailand) Ltd |
Supervision
to stack repair at Rachaburi Power Station. |
28-Apr-05 |
NEA Tuas
Incineration Plant |
Inspection, cleaning and re-brick to stack
|
6-Mar-05 |
Shell Eastern Petroleum |
Repair to HCS
stack (Replace brackets 3 & 4) plus brick
supply order. |
5-Mar-05 |
Shell
Refining Company (Federation of Malaya) Berhad
|
Consulting on damage to LRCCU stack. |
4-Mar-05 |
Leighton Malaysia |
Inspection of
1 brick lined 200m high flue. |
25-Jan-05 |
Shell
Refining Company (Federation of Malaya) Berhad
|
Inspection and repairs to 3 stacks (CD2/Plat
2/MVU). |
25-Jan-05 |
Shell Eastern Petroleum |
HCS II Steel
stack inspection access. |
24-Jan-05 |
Shell
Eastern Petroleum |
HCS repair check. |
1-Aug-04 |
Shell Eastern Petroleum |
SRU emissions
study. |
28-Jul-04 |
Shell Eastern Petroleum |
Maintenance & repair to CD3. |
26-Jul-04 |
Shell Eastern Petroleum |
New build SRU Stack. |
 |
16-Mar-04 |
Senoko
Power |
Cleaning and inspection to 1 x180m high stack. |
5-Mar-03 |
Singapore Refining Company |
CRU stack cleaning
& painting. |
18-Dec-03 |
Shell
Eastern Petroleum |
LRCCU shutdown inspection work. |
18-Dec-03 |
Shell Eastern Petroleum
|
SRU feasibility
study. |
1-Dec-03 |
Shell
Eastern Petroleum |
Maintenance & repair to CD5, Hydro, TGU
stacks. |
26-Nov-03 |
Singapore Refining Company |
CDU 2 stack
inspection & repair. |
14-Nov-03 |
Coca Cola |
Inspection to stack. |
1-Nov-03 |
Nippon Express |
Demolition and
disposal of 2No. Stacks at Jurong Power Station. |
30-Oct-03 |
Singapore
Refining Company |
Communication Tower cleaning and painting. |
16-Oct-03 |
Oil Tanking Singapore |
Inspection to
stack. |
16-Oct-03 |
Oil Tanking
Singapore |
Monthly maintenance to sprinkler system. |
11-Sep-03 |
Caltex Singapore |
Inspection and
repair to flare stack. |
9-Sep-03 |
Singapore
Refining Company |
Flare stack remedial works. |
4-Sep-03 |
Shell Eastern Petroleum |
External inspection
to CD3. |
1-Jul-03 |
Singapore
Refining Company |
HCU-2 chimney inspection. |
20-Apr-03 |
Singapore Refining Company |
Sulphur Pit
repair (701-F). |
19-Feb-03 |
Power
Seraya |
Cleaning & inspection of 9No. Steel liners. |
6-Feb-03 |
Senoko Power |
Inspection to
8No. steam stacks. |
25-Jan-03 |
RJ Crocker |
China building inspection and survey. |
16-Jan-03 |
Lafarge Malayan Cement |
Stack inspection
& testing. |
13-Jan-03 |
Tuas Power |
Stack inspection. |
5-Nov-02 |
Zelan Construction |
New design &
build chimney: 200m high x 3 x 7.5m dia internal
steel liners with Borosilicate glass block
lining. |
 |
5-Nov-02 |
Zelan Construction |
2No. X 6000m3 new design
& build reinforced concrete silos. |
 |