BEC possess a wealth of experience in the inspection,
maintenance, repair and demolition of chimneys,
tanks and silos.
We have experience managing the construction of
over 100 stacks at locations throughout the world
including Singapore, Malaysia, Taiwan, Indonesia,
Hong Kong, Philippines, Thailand, Australia, the
Netherlands and United Kingdom.
Details include single and multi-flue, refractory,
brick, steel liners with C276 and titanium linings,
structural steelwork floors, galleries, lateral
restraints and all associated works (rack &
pinion hoist, lightning protection, internal lighting,
aircraft warning lights etc.) Heights up to 350
meters. |
|
 |
| Extensive involvement in
slip form and jump shutter projects throughout the
world on structures such as high-rise buildings
(over 50), silos (23), cryogenic tanks (9), sewage
tanks and caissons (5), vent shaft linings (Channel
Tunnel), water tanks (10) and telecommunication
towers (Menara KL, Malaysia) Diameters up to 78
meters. |
|
|
| |
 |
|
| |
Zelan
Construction
BEC (M) successfully designs & builds
two (2) 42m high 6000m3 Fly Ash storage
silos |
| For more details on the project
|
 |
|
| |
|
|
Zelan
Construction
BEC (M) successfully designs & builds
one (1) 200m high reinforced concrete multiflue
chimney. |
| For more details on the project
|
 |
|
|
| |
|
 |
Shell
Refining Co. (FOM) Bhd. shutdowns.
Port DIckson refinery
Stack: MVU, Plat 2, CD2, LRCCU
Successfully completed inspections and repairs to
the above stacks during plant shutdowns. Emergency
repairs required due to emergent works during inspection.
|
|
| |
 |
 |
Shell
Eastern Petroleum Pte. Ltd. shutdowns. Pulau
Bukom refinery
Stacks: CD3, CD4, CD5,
HCU, LRCCU, HCS, HCSII, TGU
Successfully completed
inspection and repairs to the above stacks
during plant shutdowns.
Works involved major and minor repairs to
brick, steel and refractory linings.
|
|
|
Shell
Eastern Petroleum Pte. Ltd. LOC/UTL shutdown
This project involves the design and construction
of a steel liner. The liner is to be installed
inside the existing windshield replacing the
existing brick liner. |
| |
New
design & build SRU Stack
BEC (S) successfully completes from
feasibility studies through to conceptual
design and final construction the new
100m high SRU stack servicing SRU units
3 & 5 and future SRU 6 unit. |
| For more details on the
project |
 |
|
| |
|
|
|
| |
 |
|
ALSTOM
Power Asia Pacific Sdn Bhd.
Perlis Power Station Pipe Cleaning
Cleaned approx. 600m of gas supply pipeline
using the rotor fan high-pressure water system.
|
|
Seraya Power
Ltd.
Cleaning and inspection to chimney liners
This project involves the phased cleaning
and inspection work to four (4) x 180 meter
high steel liners.
Ultrasonic testing, verticality readings and
welding tests are involved to check the integrity
of the existing liners. |
|
|
Blue
Circle Materials Silo alterations
Site managing the repairs and alterations
on two 66m high bulk storage silos in Jurong
Port.
Jump shutter construction of 30m skin walls
in confined access storage cells.
Void filling using pioneering high pressure
pumping techniques. Site management team achieved
very tight programme and partial completion
dates. |
|
|
|